Niagara College marks timber-frame milestone for new Health Education Building
Ontario Construction News staff writer
Niagara College and project partners marked a construction milestone at the new Health Education Building on Nov. 10 with the signing of a structural timber beam that will become part of the 75,000-square-foot facility.
The two-storey building is expected to enable Niagara College to graduate an additional 800 students annually from its healthcare programs.
“As the timber beams go up and we see the shape and scale of Niagara College’s new Health Education Building emerge, we’re seeing what’s possible when a community comes together around a shared priority,” said college president Sean Kennedy. “Each beam represents a shared investment in our students and the future of healthcare in Niagara.”
A tree planting and a dedication ceremony at the site recognized the Myhal Family Foundation for its contributions to the project, which will house the Myhal School of Nursing.
“Supporting Niagara College’s new Health Education Building isn’t just about constructing state-of-the-art classrooms or expanding footprint; it’s about investing directly in the human pipeline that will sustain our community for generations,” said Rayla Myhal, president of the Myhal Family Foundation.
The building will include an expanded dental clinic with double the capacity to serve about 3,000 people annually, a Health and Community Hub for vaccination clinics and wellness screenings, and expanded student-run physical therapy clinics.
The project team includes Montgomery Sisam Architects and the college’s Planning and Capital Projects department.
The building will use mass timber construction, with 941 components, including columns, beams, floor and roof panels, scheduled for installation between November and January. The timber structure is expected to reduce the building’s carbon footprint compared with conventional steel and concrete construction, supporting the college’s Net Zero and Carbon Neutral goals.
Construction is being completed in two phases, with the first phase targeted for occupancy in early fall 2027. It will include an expanded dental clinic, dental materials, grinding and radiography labs, new and enhanced paramedic, virtual reality learning and pharmacy labs, a bookable multipurpose clinic and general instructional classrooms.
Phase two, scheduled for December 2028, will involve renovations to the existing Applied Health Institute, including improved massage clinic space, upgraded occupational therapy assistant and physiotherapy labs, and additional nursing lab capacity.
Design incorporates barrier-free spaces, inclusive amenities and dedicated family and parenting spaces for students and community members.